Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

February 26th, 2026

home ready for furniture install

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

88% Complete

approximate % complete

</aside>

Untitled

Risks & Notable Updates


Stair Tread Installation

Stair install needs to take place as soon as possible to ensure we have enough time to fabricate and install our interior handrail to pass C of O. Chad F. has threads scheduled to be installed next week, which should be enough time for the handrail to be produced.

Door Jamb Installation

Door jamb installation is continuing. There will be more drywall patchwork than Magleby expected which could hold up the start of paint. Chad F. is expecting to have all doors hung by 12/12.

HVAC Rework

We should be seeing demo plans by early next week from Project E, which is the engineer WPR has retained.

Construction Progress


Landscaping

Landscaping continued.

image.png

Door Jamb Installation

Door jamb installation continued.

image.png

Cabinetry Installation

Cabinetry installation continued.

image.png

Playhouse

Play house work continued.

image.png