Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

February 26th, 2026

home ready for furniture install

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

81% Complete

approximate % complete

</aside>

Untitled

Risks & Notable Updates


Decorative Metals

Innovative Iron continues to struggle to meet schedule expectations. Chad and Zach are working on getting them wrangled. The part of their scope that poses the highest risk to our schedule is the interior handrail, as it is necessary for a Certificate of Occupancy. With the holidays coming up and stair treads still not installed, there is a chance it comes down to the wire.

Door Jamb Installation

Door jamb installation started today 11/24.

HVAC Rework

WPR’s mark up of areas that will probably require rework has been shared with Magleby. Zach is putting together estimated timelines. One that assumes HVAC rework starting as soon as possible and one assuming rework is held off until after the house is turned over.

Furniture Package Approval

Britta is finalizing furniture selections. She sent a summary package to Diane for review and will share an updated budget in the next few days for approval and payment.

Construction Progress


Tile Installation

Tile installation continued last week.

image.png

Landscaping

Landscaping continued.

image.png

Wood Flooring Install

Wood flooring installation continued.

image.png