Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

February 26th, 2026

home ready for furniture install

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

81% Complete

approximate % complete

</aside>

Untitled

Risks & Notable Updates


Countertop Templating

Templating and fabrication of stone countertops has been ongoing for a week and half now. I’m hoping to get a firm delivery/install date from Magleby this week.

Door Jambs Sizing

Magleby is working with Precision Millworks to remake jambs as needed. Chad F. would like to get final paint started as soon as possible, but the jambs need to be installed before the dry waller and painter can finish their scopes.

Cabinetry Installation

Cabinetry installation progressed well last week. The focus was the office and kitchen areas.

Construction Progress


Tile Installation

Tile installation continued last week.

image.png

Landscaping

Landscaping continued.

image.png

Wood Flooring Install

Wood flooring installation continued.

image.png

Cabinetry Installation

Cabinetry installation continued.

image.png