Tile installation started today (10/28) and flooring install started late last week. Magleby is pushing to get as much tile and flooring down as quickly as possible to get cabinetry installers back on site next week.
Cabinetry installation is scheduled to start back up next week, as long as enough wood flooring and tile is installed.
We are still waiting on confirmation from Magleby regarding the construction of door jambs. They seemed to have been undersized.
Shower preparation continued last week

Ceiling T&G installation was completed last week.

Wood flooring installation started.