Schedule Variance Report

Task Baseline Date Actual Date Variance Risk
Door Jamb Install Start 8/12/25 TBD TBD Medium
Cabinetry Install Finish 11/26/25 TBD 0 Medium
Tile Start 9/16/25 10/9 + 23 Days Medium
Countertop Templating Start 10/16/25 TBD TBD Medium

“-” = no variance or if baseline date is in the future and actual date is to be determined “+##” = positive variance “-##” = negative variance “TBD” = if task is behind b/c baseline date has passed but actual date is still TBD

Project Risks

HVAC System Performance

Initial engineering reports for the first few D-lots indicate that HVAC/cooling components will need to be upsized throughout the home, and on most lots. An individual evaluation for D11 has not yet been published but it’s likely that there will be component upgrades that require some interior finish demolition and rework. Owner’s will not be responsible for improvement costs. RAG will provide more information as we learn more.

Tile Installation Start

Tile prep started in the Junior suite last week. The tile installer was held off on most shower pans due to drains needing to be moved and concrete needing to be cut back to the correct size. They should be starting install on the rest of the tiled areas this week.

Countertop Templating Start

Zach shared an updated schedule over the weekend. Due to miss sequencing trades Magleby had to add 8 days to the overall project timeline, countertop templating for the lower level is now scheduled for 10/31.

Construction Progress

Shower Pans

Plumbers reworked drain locations ahead of starting the shower pans.

image.png

Ceiling T&G

Ceiling T&G installation continued this week.

image.png

Cabinetry

Cabinetry install continued.

image.png