| Task | Baseline Date | Actual Date | Variance | Risk |
|---|---|---|---|---|
| Door Jamb Install Start | 8/12/25 | TBD | TBD | Medium |
| Cabinetry Install Finish | 11/26/25 | TBD | 0 | Medium |
| Tile Start | 9/16/25 | 10/9 | + 23 Days | Medium |
| Countertop Templating Start | 10/16/25 | TBD | TBD | Medium |
“-” = no variance or if baseline date is in the future and actual date is to be determined “+##” = positive variance “-##” = negative variance “TBD” = if task is behind b/c baseline date has passed but actual date is still TBD
Initial engineering reports for the first few D-lots indicate that HVAC/cooling components will need to be upsized throughout the home, and on most lots. An individual evaluation for D11 has not yet been published but it’s likely that there will be component upgrades that require some interior finish demolition and rework. Owner’s will not be responsible for improvement costs. RAG will provide more information as we learn more.
Tile prep started in the Junior suite last week. The tile installer was held off on most shower pans due to drains needing to be moved and concrete needing to be cut back to the correct size. They should be starting install on the rest of the tiled areas this week.
Zach shared an updated schedule over the weekend. Due to miss sequencing trades Magleby had to add 8 days to the overall project timeline, countertop templating for the lower level is now scheduled for 10/31.
Plumbers reworked drain locations ahead of starting the shower pans.

Ceiling T&G installation continued this week.

Cabinetry install continued.