Schedule Variance Report

Task Baseline Date Actual Date Variance Risk
Drywall Hang Completion 9/4/25 9/9/25 +5 days Complete
Door Jamb Install Start 8/12/25 TBD TBD Medium
Drywall Tape Finish Lower Level Completion 9/4/25 9/12/25 +8 days Complete
Floor Prep Start 9/1/25 (Not reflected in schedule) TBD TBD High
HVAC System Performance - - - High
Lower Level Prime and First Coat Start 9/5/25 9/14/25 + 9 Days Complete
Cabinetry Lower Level Start 9/15/25 9/15/25 0 Complete
Aero barrier Start 10/8/25 9/13/25 - 31 days Complete
T&G Ceilings Start 9/30/25 9/30/25 0 Complete
Tile Start 9/16/25 TBD TBD Medium
Countertop Templating Start 10/16/25 TBD TBD Medium

“-” = no variance or if baseline date is in the future and actual date is to be determined “+##” = positive variance “-##” = negative variance “TBD” = if task is behind b/c baseline date has passed but actual date is still TBD

Project Risks

Door Jamb Install Start

We are waiting on a delivery date from Precision Millworks, but they have all the information they need to get the door slabs and jambs stained. Unfortunately, the jambs were prepped for the wrong kind of strike plates. Magleby is working with Precision on a path forward. They will either have to pay for different strike plates from Earth Elements or remake the jambs.

HVAC System Performance

The 3rd party consultant that was engaged by Dahlin Group has begun evaluating the required cooling loads of each individual home based on aspect and floor plan. We are awaiting a formal timeline from WPR with analysis completion dates for each home.

Floor Prep Start

Floor prep did not take place last week, it is scheduled to start on Monday (10/6).

Tile Installation Start

Tile prep did not start last week, Magleby is now reporting shower pan prep will start Monday (10/6). RAG continues to check on this progress and push to get tile install started.

Countertop Templating Start

We met with Magleby to discuss the best path forward on Friday (10/3). Cabinets will need to be removed and re-installed for proper tile installation in a few areas. Zach is planning on meeting with Craftsman and the flooring installers to finalize a timeline. Once this is done we will be able to identify any delays to templating and our critical path.

Construction Progress