Schedule Variance Report

Task Baseline Date Actual Date Variance Risk
Drywall Hang Completion 9/4/25 9/9/25 +5 days Completed
Door Jamb Install Start 8/12/25 TBD TBD Medium
Drywall Tape Finish Lower Level Completion 9/4/25 9/12/25 +8 days Completed
Floor Prep Start 9/1/25 (Not reflected in schedule) TBD TBD High
HVAC System Performance - - - High
Lower Level Prime and First Coat Start 9/5/25 9/14/25 + 9 Days Complete
Cabinetry Lower Level Start 9/15/25 9/15/25 0 Complete
Aero barrier Start 10/8/25 9/13/25 - 31 days Complete
T&G Ceilings Start 9/30/25 TBD TBD Low
Tile Start 9/16/25 TBD TBD Medium

“-” = no variance or if baseline date is in the future and actual date is to be determined “+##” = positive variance “-##” = negative variance “TBD” = if task is behind b/c baseline date has passed but actual date is still TBD

Risks

Prior Applicable Risks

Door Jamb Install Start

Context: Door slabs and door jambs have been delivered. However, door slabs were not prepped for hardware. Magleby is planning on sending the door jambs and doors to Precision Millworks so that they can mortise the door slabs to match the jambs exactly.

Mitigation Plan: Magleby is moving forward with drywall tape and will touch up the drywall finish around the door jambs once installed.

09.05 Updates: Precision is planning on staining doors and door jambs while they are in their shop. We are currently working through samples to finalize the finish.

09.14 Updates: Sample review and approval ongoing.

09.20 Updates: Decision on finish should be shared early next week.

HVAC System Performance

Context: A potential issue with the North Village Single Family homes’ HVAC systems has been identified.

Mitigation Plan: WPR, Dahlin, and Magleby are working together to review the situation and identify a solution as soon as possible. This is a high priority item RAG is monitoring closely. We will keep you updated as soon as there are any developments.

09.05 Updates: Dahlin has engaged a mechanical engineer to review and design a solution to address the HVAC design so that the home cools to 68 degrees on the hottest days of the year. We expect to have further updates by the end of next week or beginning of the following week.

09.14 Updates: Pending analysis and due diligence from WPR.

09.20 Updates: Still waiting on direction from WPR.

Tile Installation Start

Context: Tile installation generally occurs prior to cabinetry being installed as it is difficult or impossible to lay the tile beneath the cabinetry once it is in place. Unfortunately, cabinetry is being installed ahead of tile. Tyler has a plan to install tile under all cabinetry, however, there’s a chance that the cabinetry in the laundry room will need to be removed and re-installed to install the tile properly.