| Task | Baseline Date | Actual Date | Variance | Risk |
|---|---|---|---|---|
| Drywall Hang Completion | 9/4/25 | TBD | TBD | Medium |
| Interior Stairs Completion | 2/19/25 | 8/20/25 | + 180 days | Completed |
| Door Jamb Install Start | 8/12/25 | TBD | TBD | High |
| Drywall Tape Finish Lower Level Completion | 9/4/25 | TBD | TBD | High |
| Floor Prep Start | 9/1/25 (Not reflected in schedule) | TBD | TBD | High |
| HVAC System Performance | - | - | - | High |
| Lower Level Prime and First Coat Start | 9/5/25 | TBD | TBD | High |
| Cabinetry Lower Level Start | 9/15/25 | TBD | - | Medium |
| Aero barrier Start | 10/8/25 | TBD | - | Medium |
“-” = no variance or if baseline date is in the future and actual date is to be determined “+##” = positive variance “-##” = negative variance “TBD” = if task is behind b/c baseline date has passed but actual date is still TBD
Context: Door slabs and door jambs have been delivered. However, door slabs were not prepped for hardware. Magleby is planning on sending the door jambs and doors to Precision Millworks so that they can mortise the door slabs to match the jambs exactly.
Mitigation Plan: Magleby is moving forward with drywall tape and will touch up the drywall finish around the door jambs once installed.
09.05 Updates: Precision is planning on staining doors and door jambs while they are in their shop. We are currently working through samples to finalize the finish.
Context: A potential issue with the North Village Single Family homes’ HVAC systems has been identified.
Mitigation Plan: WPR, Dahlin, and Magleby are working together to review the situation and identify a solution as soon as possible. This is a high priority item RAG is monitoring closely. We will keep you updated as soon as there are any developments.
09.05 Updates: Dahlin has engaged a mechanical engineer to review and design a solution to address the HVAC design so that the home cools to 68 degrees on the hottest days of the year. We expect to have further updates by the end of next week or beginning of the following week.
Context: Prime and first coat is currently scheduled for 9/11, almost a week behind schedule, which leaves no room for error on the tape and mud that should be finished on 9/10. Walls should be primed/first coated before cabinetry is installed. The Magleby team is currently targeting a 9/15 cabinetry install which may push if the painter can’t finish his work in time.
Mitigation Plan: From speaking with Magleby, the painters are comfortable finishing their scope before the 9/15 cabinetry start date. Tapers should be working weekends to accelerate schedule as well.
Context: Cabinetry is currently scheduled to be delivered on 9/15. This is a medium risk as it seems like trades are bought in to make this happen, however, any delays on drywall finish, and prime and first coat could hold them up.
Mitigation Plan: Magleby is pushing trades to finish in time for cabinetry to begin as scheduled.