Schedule Variance Report

Task Baseline Date Actual Date Variance Risk
Drywall Hang Completion 8/14/25 TBD 0 Medium
Interior Stairs Completion Not shown on schedule Not shown on schedule N/A High
Door Jamb Install Start 8/12/25 TBD N/A High

Risks

Drywall Hang

Context: Progress has been steady this week, Magleby seems to have resolved most framing issues. This is a medium risk because there is a chance this activity will be held up by stair and door jamb install.

Interior Stairs

Context: Innovative Iron made a mistake during fabrication and are now working on re-fabricating the upper part of the stairs. This is a high risk item because no install date has been defined and if not resolved it will prevent the drywall hanging from being completed.

Door Jamb Install

Context: Door Jambs are scheduled to be delivered Monday and installed Tuesday. This is a high risk item because across our other lots delivery delays are common. If this is not completed

Construction Progress

Drywall Hang

Drywall hang has been the main activity ongoing this week.

Copy of project_88030598_08082025_1511.jpg

project_88030598_08082025_1501.jpg

project_88030598_08082025_1503.jpg

project_88030598_08082025_1502.jpg

Staircase Install

Staircase install has only been finished to the lower floor. Magleby is waiting on an install date for the rest of it from Inovative Iron. This will hold up the finish of drywall hang if it doesn’t happen next week.

project_88030598_08082025_1504.jpg

Door Jamb Install

Door jambs are scheduled to be installed on 8/12. This is in line with their schedule, however, if this does not happen it will delay drywall finish, as they need to tie in their bead to the side of the jambs before taping them in.

project_88030598_07212025_1744.jpg

Commentary

Challenges - Staircase and Door Jambs

The biggest challenges that could slow down work are the door jambs not being installed as well as the staircase not being installed. They are high risk because we have not seen components like these being delivered and installed on our other lots in a timely manner. We will have a better idea next week as to when drywall will be completed based on whether or not they are able to meet their schedule on these scopes.