Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

August 7th, 2026

home ready for furniture install

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

89% Complete

approximate % complete

</aside>

Untitled

Risks & Notable Updates


HVAC Rework

Magleby has confirmed that the HVAC rework inside the home is substantially complete. They plan to test the system early next week, and if everything performs as expected, they will begin reassembling the house.

Stair Rework

The stair rework is progressing slowly, but installation of the wood treads has begun and is approximately 25% complete. At this time, the slower pace is not impacting the overall schedule.

Landscape/Easement

We are still awaiting an official response from the DRB regarding the proposed relocation of the backyard trees closer to the property line.

Construction Progress


HVAC Rework

HVAC rework is substantially complete.

image.png

Beam Stain

Beam stain installation in the great room has started.

image.png

Staircase Rework

The staircase rework is still on going.

image.png

Kitchen Island

Finish panel being installed under island countertop

image.png