Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

August 7th, 2026

home ready for furniture install

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

88% Complete

approximate % complete

</aside>

Untitled

Risks & Notable Updates


HVAC Rework

HVAC is the critical path. Most ducting and line sets are complete, with final connections, testing, and commissioning scheduled for May 11–12, followed by a Matterport on May 18th, and final wall/ceiling close-up through the end of May.

Stair Rework

Steel structure is complete and finished; tread installation was slightly delayed but starting this week and not expected to impact schedule.

Interiors

Interior finishes (tile, slabs, plumbing fixtures) must be sequenced around HVAC work, but are progressing steadily.

Exterior

Handrails are underway and the exterior teams are completing siding and stone fixes around the flex deck.

Landscape/Easement

We are currently awaiting an official response from the DRB regarding the proposed relocation of the backyard trees closer to the property line.

In the meantime, the easement agreements are ready for execution. Please confirm your preferred method for signing and notarizing the documents. Carley is available to coordinate an electronic notary if that is your preference. Alternatively, if you would prefer to proceed with wet signatures, please send the completed, notarized copies to:

Wasatch Peaks Ranch c/o Carley Herrick 36 South State Street, Suite 500 Salt Lake City, UT 84111

Construction Progress