Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

August 7th, 2026

home ready for furniture install

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

86% Complete

approximate % complete

</aside>

Untitled

Risks & Notable Updates


HVAC Rework Coordination

HVAC rework is now underway throughout the home. Authority HVAC, along with the new HVAC engineer Paul Greenwood, have been actively working through RFIs. Chad F. shared that Authority is confident they can complete the work within 15 working days, provided they receive timely responses to outstanding questions. If that timeline holds, we should be in a good position from a schedule standpoint.

Staircase Rework

The staircase rework has experienced some delay, though it is not expected to impact the critical path. Innovative Iron is currently scheduled to return to site next Tuesday (4/21) to complete the remaining steel work. Following that, Chad has carpenters lined up for 4/27 to begin reinstallation of the wood treads.

Construction Progress


HVAC Rework

HVAC rework is underway throughout the home.

image.png

Tile Installation

Tile installation continued.

image.png

Staircase Rework

The staircase rework is still on going. Innovative Iron has made minimal progress since the last update, however, this should not impact critical path.

image.png

Stoop Step In Garage

The stoop step was poured in the garage.

image.png