Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

August 7th, 2026

home ready for furniture install

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

84% Complete

approximate % complete

</aside>

Untitled

Risks & Notable Updates


HVAC Rework Coordination

The HVAC AWA has been executed, and Zach has issued contracts to subcontractors to begin work as soon as possible. Magleby is pushing for Authority HVAC to mobilize as soon as possible.

Staircase Rework

Innovative Iron is expected to complete the realignment of the structural steel staircase components by Wednesday of this week. Carpenters are currently on site preparing the wood treads for installation, with Magleby targeting the start of wood tread reinstallation by the end of this week.

Construction Progress


Beam Touch Ups

Decorative beam joints were sanded down to make sure they aligned properly.

image.png

Tile Installation

Tile installation continued.

image.png

Staircase Rework

The steel portion of the stair rework is almost complete, Innovative Iron should be finished early next week.

image.png

Prime and First Coat

Painters have started final paint in the lower bedrooms. Magleby has started doing quality control work and will be bringing back the tapers and painters to address deficiencies.

image.png

Client Decisions