Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

February 26th, 2026

home ready for furniture install

Date to be updated once HVAC rework schedule is issued

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

93% Complete

approximate % complete

Percentage complete to be updated once HVAC rework schedule is issued

</aside>

Untitled

Risks & Notable Updates


HVAC Rework

Preliminary demolition is underway throughout the home. We are awaiting confirmation of the remaining HVAC rework budget and an updated construction schedule from Magleby. Zach shared a draft schedule this morning, and we will review and provide comments today. We are also expecting an update from the HVAC subcontractor following their walkthrough to assess the retrofit complexity now that demolition is wrapping up.

Interior Handrail

We informed Magleby that the modified handrail design was not approved and that the original design is to be installed. Chad F. is working on a solution to help minimize rework; however, Magleby is committed to delivering a handrail that aligns with the original design intent.

Construction Progress


Countertop Installation

Counter top installation continued.

image.png

Tile Installation

Tile installation continued.

image.png

HVAC Demolition

Ceiling demolition is ongoing throughout the home.

image.png

Plaster

The first coat of plaster is being installed throughout the main level.

image.png

Cabinetry rework

Cabinets were modified to meet design intent in bedroom 1.

image.png

Baseboard Installation

Baseboard installation began in the basement.

image.png