<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />
home ready for furniture install
Date to be updated once HVAC rework schedule is issued
</aside>
<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />
approximate % complete
Percentage complete to be updated once HVAC rework schedule is issued
</aside>
Preliminary demolition is underway throughout the home. We are awaiting confirmation of the remaining HVAC rework budget and an updated construction schedule from Magleby. Zach shared a draft schedule this morning, and we will review and provide comments today. We are also expecting an update from the HVAC subcontractor following their walkthrough to assess the retrofit complexity now that demolition is wrapping up.
We informed Magleby that the modified handrail design was not approved and that the original design is to be installed. Chad F. is working on a solution to help minimize rework; however, Magleby is committed to delivering a handrail that aligns with the original design intent.
Counter top installation continued.

Tile installation continued.

Ceiling demolition is ongoing throughout the home.

The first coat of plaster is being installed throughout the main level.

Cabinets were modified to meet design intent in bedroom 1.

Baseboard installation began in the basement.