Schedule


<aside> <img src="/icons/flag-checkered_gray.svg" alt="/icons/flag-checkered_gray.svg" width="40px" />

February 26th, 2026

home ready for furniture install

Date to be updated once HVAC rework schedule is issued

</aside>

<aside> <img src="/icons/chart-area_gray.svg" alt="/icons/chart-area_gray.svg" width="40px" />

93% Complete

approximate % complete

Percentage complete to be updated once HVAC rework schedule is issued

</aside>

Untitled

Risks & Notable Updates


HVAC Rework

We are currently in a holding pattern until budgets are approved by WPR for the HVAC re-work. I followed up with Zach yesterday about the demolition bid they have already received, but I haven’t seen anything yet. Zach conveyed that WPR is waiting on a budget from Magleby for all of the HVAC rework before approving the demolition costs. Magleby has committed to having the budget finalized for approval today (2/6).

Interior Handrail

Stair tread installation was wrapped up this week, however, the treads were not built to the correct dimensions and the initial handrail design will not work without some major remodeling. We are currently waiting on drawings from Innovative Iron for a handrail that will work with the stair treads as they are installed. Magleby may have to take the stairs apart and re-install them in conformance with the architectural drawings if they have to deviate heavily from the design intent.

Construction Progress


Countertop Installation

Counter top installation continued.

image.png

Hardscape

Edging installation is ongoing.

image.png

Tile Installation

Tile installation continued.

image.png

Exterior Masonry

Masonry was installed on front patio walls.

image.png

Beam Stain

Painters started to stain the wood beams.

image.png

Stair Tread Installation

Stair tread installation completed.

image.png